Team rooms in the new Auxiliary gym at the Junior-Senior High School walls are going up.
Junior - Senior High School Main Gymnasium floor is almost finished and looks stunning!
Northeast doors on the Junior- Senior High School have been painted "Cougar Blue".
New Condensing Boiler arrived at the Junior-Senior High School and will be installed soon.
Final Exterior bricks are now installed on the new Auxiliary gym.
Phase 2 roofing repairs have begun. Here are some before and after pictures of items fixed at the current Middle School. More work will be done next spring.
The new floor was poured in the Auxiliary gym and now needs to cure for 60 days.